Can I check which vendors started a submission but did not finish?

Bonfire gives you visibility on Vendors' Submissions including the proposals that were not submitted.

If for any reason you need to take a look into the Vendors that started a Submission but did not submit at the end, you will be able to view this under the Work-in-Progress Submissions located on the Submissions page:

WIP

Click "Show the Work-In-Progress Submissions" link.

WIP

By expanding the view to show the suppliers, you will be able to view details such as:

  • Supplier - The Supplier's Name
  • Created - The day they started their proposal
  • Progress - How far along the submission is towards completion
  • Optional* - Diversity or Subcontractor Information
  • Type - shows if the Submission was either External (made by the Vendor) or Internal (made by the Project Owner).

The Work-in-progress submissions feature lets you see which vendors have started preparing their submissions so you can get a sense of how many bids are likely to come in. The formula for the progress bar is:

%β€ˆ=β€ˆπ‘…π‘’π‘žπ‘’π‘’π‘ π‘‘π‘’π‘‘β€ˆπΌπ‘›π‘“π‘œπ‘Ÿπ‘šπ‘Žπ‘‘π‘–π‘œπ‘›β€ˆπ‘ π‘™π‘œπ‘‘π‘ β€ˆπ‘ π‘Žπ‘£π‘’π‘‘ / π‘‡π‘œπ‘‘π‘Žπ‘™β€ˆπ‘…π‘’π‘žπ‘’π‘’π‘ π‘‘π‘’π‘‘β€ˆπΌπ‘›π‘“π‘œπ‘Ÿπ‘šπ‘Žπ‘‘π‘–π‘œπ‘›β€ˆπ‘ π‘™π‘œπ‘‘π‘ β€ˆxβ€ˆ100%

NOTE: Optional slots do not count towards the progress bar percentage. 

 

 